Compliance & Site Requirements

Codes & standards · food safety · foundation · services interface · site plan

Codes & standards

AreaStandardNotes
Electrical safetyIEC 60204-1 (machinery electrical equipment)Emergency stop circuit, lockable isolator
Refrigerant safetyASHRAE 15 / EN 378Leak detector in room, refrigerant relief
Food contact materialsEU 1935/2004 / FDA 21 CFRAll product-contact surfaces AISI 304 SS or food-grade polymer
Pressure equipmentASME B31.5 / EN 14276 (if applicable)Refrigerant pressure vessels, factory-certified
HygieneEHEDG guidelines for dry-food equipmentCoved corners, drainable, no dead legs
Motor efficiencyIE3 (IEC 60034-30-1)All motors ≥ IE3; fans on VFD

Food safety & HACCP

Foundation & floor loading

Trolleys (16 × ~170 kg)2.7 t
Product (fresh coconut)1.8 t
Insulated panels + structure~0.8 t
Total dead + live load~5.3 t
Floor area32 m²
Average floor load1.6 kN/m²
Wheel point load (worst case)~0.7 kN per wheel (4 per trolley)
Slab specification150 mm reinforced concrete, design load 3.0 kN/m², polyurethane-topped
S9 — Site plan: room in context with electrical supply, water, condensate drain, service clearances, and floor-loading summary.
S9 — Site plan: room in context with electrical supply, water, condensate drain, service clearances, and floor-loading summary.

Services interface (by others — not in vendor scope)

ServiceSpecificationInterface point
Electrical supply3-phase 415 V + N + E, 100 A isolator within 3 m of HP unitIsolator terminal
Water (potable)1/2" hosepoint at door, for wash-downBall valve at wall
Condensate drain32 mm PVC/SS to building drain or recovery tankRoom floor trap
Floor slab150 mm RC, 1:100 slope to door-end, coved edgesTop of slab
Building structureRoof load: panels ~12 kg/m²; no structural load from dryerPanel support
Ventilation (HP room)If HP unit is in a separate plant room: 5 air changes/h for heat rejection

Vendor scope boundary

The vendor supplies the heat-pump dehumidifier modules, fans, trolleys, trays, control panel, sensors, and commissioning. The following are NOT in scope (by others):

← 9 · Business casePage 10 of 1211 · Vendor →