Operation Cycle

Batch timeline · maintenance · quality checks

Batch timeline (per day)

Load1.0 h
Stage 1 @ 55°C0.9 h
Stage 2 @ 62°C5.2 h
Stage 3 @ 65°C13.6 h
Cool & unload1.0 h

Total cycle: ~21.7 h · 1 batch/day with 2.3 h margin for cleaning & turnaround.

Loading procedure

  1. Wheel trolleys to the loading dock; load shelled halves onto trays at 10 kg/m² (single layer, equator up).
  2. Wheel trolleys into the room — 16 trolleys in 2-abreast × 4 along configuration.
  3. Confirm door closed and interlocked; start batch from HMI.

Quality checks

CheckMethodTarget
Final moisture contentHalve 10 random halves, oven 105°C / 24 h5.0 ± 0.5% wb
Moisture uniformity across batchSample top/mid/bottom tray of each channelσ < 0.4%
ColourVisual vs referenceWhite to pale cream; no brown scorch
Condensate mass balanceTank volume vs final MCWithin ±5%

Maintenance schedule

FrequencyTask
Each batchInspect and clean tray mesh; check condensate tank
WeeklyClean evaporator/condenser coils; verify sensor calibration
MonthlyInspect fan belts/bearings (if any); check refrigerant sight-glass
AnnuallyRefrigerant charge check; compressor oil sample; pressure-test safety circuit